Project portfolio / 01

Permanent noise barrier projects.

Explore the rail and highway references from our company profile, with project scope and photo galleries.

Permanent Noise Barriers

Selected references.

Rail InfrastructureMarch 2013 - April 2016

PROJECT 01

MRT Sungai Buloh-Kajang Line

KVMRT Line 1 - SBK

Client
Mass Rapid Transit Corporation Sdn Bhd
Scope
Design, supply, installation, testing and commissioning of noise barriers and enclosures for the Mass Rapid Transit Jajaran Sungai Buloh-Kajang (SBK Line - KVMRT Line 1).

Key highlights

  • Over 8,900 tonnes of steel structure
  • Over 93,000 m² of acoustic and transparent PMMA noise barrier panels
  • Over 109,000 m² of architectural expanded metal
  • Over 16.7 km of noise barriers and enclosures
Rail InfrastructureDecember 2017 - January 2023

PROJECT 02

MRT Sungai Buloh-Serdang-Putrajaya Line

KVMRT Line 2 - SSP

Client
Mass Rapid Transit Corporation Sdn Bhd
Scope
Design, supply, installation, testing and commissioning of noise barriers and enclosures for the Mass Rapid Transit Jajaran Sungai Buloh-Serdang-Putrajaya (SSP Line - KVMRT Line 2).

Key highlights

  • Over 7,900 tonnes of steel structure
  • Over 115,000 m² of acoustic and transparent PMMA noise barrier panels
  • Over 16.5 km of noise barriers and enclosures
Highway InfrastructureJanuary 2019 - September 2022

PROJECT 03

Damansara-Shah Alam Elevated Expressway

DASH Expressway

Client
Turnpike Synergy Sdn Bhd
Scope
Design, supply, installation, testing and commissioning of noise barriers for the Damansara-Shah Alam Elevated Expressway (DASH).

Key highlights

  • Over 1,700 tonnes of steel structure
  • Over 43,000 m² of acoustic and transparent PMMA noise barrier panels
  • Full-enclosure noise barrier spanning 30 metres
  • Over 11 km of noise barriers and enclosures plus 200 m of masonry noise barrier
Highway InfrastructureJanuary 2019 - March 2023

PROJECT 04

Sungai Besi-Ulu Kelang Elevated Expressway

SUKE Expressway

Client
Turnpike Synergy Sdn Bhd
Scope
Design, supply, installation, testing and commissioning of noise barriers for the Sungai Besi-Ulu Kelang Elevated Expressway (SUKE).

Key highlights

  • Over 2,700 tonnes of steel structure
  • Over 53,000 m² of acoustic and transparent PMMA noise barrier panels
  • Over 18.5 km of noise barriers and enclosures
Rail InfrastructureMarch 2018 - November 2023

PROJECT 05

Light Rail Transit Line 3

LRT3 Bandar Utama-Johan Setia

Client
Setia Utama LRT3 Sdn Bhd
Scope
Design, supply, installation, testing and commissioning of noise barriers for the Light Rail Transit Line 3 project from Bandar Utama to Johan Setia.

Key highlights

  • Over 41,000 m² of acoustic and transparent PMMA noise barrier panels
  • Over 36 km of noise barriers